Friday, February 1, 2008

Calendar: MP4

Week 1 (Feb. 4 - 9):

“Procure” the necessary programs/hardware:
a. Adobe Flash (For scripting/animation)
b. Adobe Photoshop (For creating scenes/characters)
c. Computer (To specs. Listed in BoM)
d. Scanner
e. Sound Recorder/Playback
f. Audacity

Week 2 (Feb. 12 - 17):

• Import Photoshop files into Flash,
• Use imported files to create animated sequences.
• Use Audacity to record music/dialogue

Week 3 (Feb. 20 - 25):

• Import Photoshop files into Flash,
• Use imported files to create animated sequences.
• Use Audacity to record music/dialogue

Week 4 (Feb. 28 – March 4)

• Import Photoshop files into Flash,
• Use imported files to create animated sequences.
• Use Audacity to record music/dialogue

Week 5 (March 7 - 12):

Compile scripting/animation sequences into playable game

Week 6 (March 15 - 20):

• Use Testing Procedure to gauge appeal/functionality of game. Repeat above steps until project is completed to specifications as outlined in Selection/Rejection Report.
• Mentor contacts
• Solution Assessment

Week 7 (March 23 - 28)

• Use Testing Procedure to gauge appeal/functionality of game. Repeat above steps until project is completed to specifications as outlined in Selection/Rejection Report.

Week 8 (March 31 – April 5)

• Presentations. Marking period ends this week.